Beef trim management blending system
30 May 2018
Focus area: Carcase primal profitability optimisation
Program stream: Advanced manufacturing
Project number: 2016-1118
The Beef Trim Management and Blending System has proven to successfully improve CL accuracy of packed trim by 0.456% and removed CL rejects associated with manually grading trim. Furthermore, the system improves carton packing labour efficiency through the utilisation of a Multibatcher which has the throughput of 3 operators.
Key learning from the project are:
• Consistent product flow to the Eagle FA/3 x-ray is critical
• Smaller, sliced trim prices improve overall carton CL accuracy
• Consistent feed to the Cabinplant Multibatcher is critical
• Where possible Intralox thermodrive belts can be used however 800 Series Nub Top belts are best for incline scenarios. 0470